Demand Assesment for Incremental capacity 2021
Status: Closed
Last update: 22 October 2021
Publication of market demand assessment report (DAR) for incremental capacity
22 October 2021
From 5 July 2021 to 30 August 2021 BBL Company (BBLC) has asked the market for its non-binding interest in incremental capacity on the Bacton IP of the BBL Interconnector. BBLC together with its neighboring TSO National Grid herewith publishes the market demand assessment report for IP Bacton.
Download
Demand Assesment for Incremental capacity
5 July 2021
BBLC hereby announce that it will accept non-binding demand indications for a period of 8 weeks. This demand assessment is a first step within the incremental capacity process described by NC CAM (Regulation 2017/459). Interested parties are invited to submit indications until 30 August 2021 with use of the attached template.
The key dates for this market demand assessment are as follows:
Activity | Date |
---|---|
Publication of market demand indication document | 5 July 2021 |
Market demand indication window open | 8 weeks |
Market demand indication window closed | 30 August 2021 |
Market demand assessment report publishes | No later than 25 October 2021 |